1. Sadie works as an electronics design engineer in a major corporation. Sadie's average work queue (including...

Question:

1. Sadie works as an electronics design engineer in a major corporation. Sadie's average work queue (including the job she is currently working on) averages 10 design projects. Her average time to complete an individual job is one week. Management, realizing Sadie represents very expensive and rare talent, monitors her utilization very closely and assigns her work as necessary to keep her utilization at 95%. What is Sadie's average lead time (time in queue plus processing time)?

2. Concerned project lead time is too high, management is considering the purchase of a new electronic design software package they believe will enhance Sadie's productivity. Suppose they purchase the new software and find Sadie's average time to complete an individual job drops from 1 week to 0.8 work (4 days). Assume the new software has no impact on the variability of the time it takes Sadie to complete an individual job. Suppose management does not increase the number of jobs (arrival rate) Sadie has to do. After adopting the software, what will be Sadie's new average lead time?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: