8 Environment Recycling Inc must clean up a large automobile tire
8. Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. The tasks, durations (in weeks), costs, and predecessor relationships are shown as follows:
a. Draw the project network.
b. Identify the critical path(s).
c. What is the total project completion time and total cost?