A bridge is to be constructed now as part of a new road. An analysis has shown
Question:
Widen Bridge In Probability
3 years ................................... 0.1
4 years ................................... 0.2
5 years ................................... 0.3
6 years ................................... 0.4
The present estimated cost of the two-lane bridge is $2,000,000. If constructed now, the four-lane bridge will cost $3,500,000. The future cost of widening a two-lane bridge will be an extra $2,000,000 plus $250,000 for every year that widening is delayed. If money can earn 12% per year, what would you recommend?