A farm owner is going to erect a maintenance building
A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table:


Construct the network for this project, identify the critical path, and determine the project durationtime.