a. One hundred twenty units of end item Z are needed at the beginning of week 7.
Question:
b. Ninety-five units of end item E are needed at the beginning of week 7. Prepare a material requirements plan for component D. Take into account that 5 units of E are currently on hand, as well as 50 units of B, 100 units of C, and 80 units of D. Also, 30 units of C have been outsourced and are expected to arrive in week 4. Lead times are two weeks for E and C, and one week for the other components. Assume lot-for-lot ordering except for D, where multiples of 40 must beused.