A probabilistic network has a critical path of 21 days and a .95 probability of completing this
Question:
A probabilistic network has a critical path of 21 days and a .95 probability of completing this path in 24 days. Therefore, the project has a .95 chance of being finished by the end of the 24th day. True or False? Briefly explain your answer.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 84% (13 reviews)
False Only the path claimed to be critical has a 95 percent chance of being completed within ...View the full answer
Answered By
Anoop V
I have five years of experience in teaching and I have National Eligibility in teaching (UGC-NET) .
5.00+
1+ Reviews
10+ Question Solved
Related Book For
Project Management in Practice
ISBN: 978-0470533017
4th edition
Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco
Question Posted:
Students also viewed these Management Leadership questions
-
True or false Briefly explain in each case. a. Lenders in project financings rarely have any recourse against the projects owners if the project fails. b. Many new and exotic debt securities are...
-
A CPM/PERT project network has probabilistic activity times (x) as shown on each branch of the network; for example, activity 13 has a .40 probability that it will be completed in 6 weeks and a .60...
-
Answer true or false for below Exercises. If false, explain why. 1. It is possible to find the complement of a 120° angle. 2. The supplement of a 5° angle is a 175° angle. 3. Below is a...
-
Ava bought a house on 1 July 2000 for 62,000. She occupied the entire property as her PPR until 1 August 2007 when she began using one-quarter of the house for business purposes. This continued until...
-
How might moral intensity influence the decisions made by accounting professionals?
-
In what follows, write the expression for H 0 according to the given H 1 . a) H 1 > 103.2 , b) H 1 < 547 , c) H 1 706.44 , d) H 1 0.75 , e) H 1 1 2 > 0 , f) H 1 at least one...
-
Determine the static pressure to stagnation pressure ratio associated with the following motion in standard air: (a) a runner moving at the rate of \(10 \mathrm{mph}\), (b) a cyclist moving at the...
-
Richard, age 45, is married with two children in high school. He estimates that his average annual earnings over the next 20 years will be $60,000. He estimates that one-third of his average annual...
-
Imagine a vendor responded to your request for a HRIS proposal. What are the indirect/direct costs and benefits of the HRIS? What is the cost of implementation (include dollar estimates)? Does the...
-
Traditionally firms raise capital in the primary market issuing either fixed or floating rate debt. Both bond structures expose the firm to interest rate risk. The financial derivatives market...
-
When using AON networks, how does one indicate an event such as a project milestone?
-
Not uncommonly, the Gantt chart is deceptive in its apparent simplicity. Briefly explain.
-
Two alternative investment opportunities are available to Nina Crews, president of Crews Enterprises. For the first alternative, the present value of cash inflows is $148,000, and the present value...
-
Which one of the following input-output relationship is that of a linear system 1. 3. Output 5 0 Output 0 0 Input Input 2. 4. Output Output 0 0 Input Input
-
Why do we need standards for the graphical elements of diagrams?
-
Why is a corporation considered an artificial person under the law? What are the consequences of this concept?
-
Determine which of the following second order systems are underdamped, which are critically damped and which are overdamped. (a) \(\mathrm{T}(s)=\frac{9 s^{2}+3 s+10}{s^{2}+5 s+2}\) (b)...
-
Feedback control systems are (a) insensitive to both forward and feedback path parameter changes (b) less sensitive to feedback path parameter changes than to forward path parameter changes (c) less...
-
Identify which control activity is violated in each of the following situations, and explain how the situation creates an opportunity for a fraud. 1. The person with primary responsibility for...
-
Review Exhibit 11.4. Analyze each product on the graph according to the characteristics that influence the rate of adoption. For example, what can you conclude from the data about the relative...
-
For each of the following differential equations write down the differential operator L that would enable the equation to be expressed as L[x(t)] = 0: dx (a) = f(t)x dt (b) (c) (e) 60 dx dt (h) dx dt...
-
A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI.
-
A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and...
-
A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three...
-
29. You are standing on a balcony on the 15th floor of the Bank of America building in San Francisco. The balcony is 72 m above the ground; the top of the building is 52 floors (237 m) high. You...
-
(a) What is the kinetic energy in joules of a 1140-kg automobile traveling at 93 km/h? (b) How much work would have to be done to bring a 1140-kg automobile traveling at 93 km/h to a stop? 4. How...
-
A block of mass 2 kg is attached to a spring with a spring constant of 100 N/m. The block is released from rest and moves along a rough horizontal surface with a coefficient of friction of 0.2. How...
Study smarter with the SolutionInn App