A process engineer is considering two sampling plans. In the first, a sample of 10 will be

Question:

A process engineer is considering two sampling plans. In the first, a sample of 10 will be selected and the lot accepted if 3 or fewer are found defective. In the second, the sample size is 20 and the acceptance number is 5. Develop an OC curve for each. Compare the probability of acceptance for lots that are 5, 10, 20, and 30% defective. Which of the plans would you recommend if you were the supplier?