A production line has four workstations and a 50- second cycle time. The total amount of actual

Question:

A production line has four workstations and a 50- second cycle time. The total amount of actual task time across all four workstations is 170 seconds. What is the idle time? The percent idle time? The efficiency delay?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: