Question

A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.


a. Construct a network diagram. You can use either AOA or AON (see Example 5).


b. If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $ 1,000; and if the project is finished within 27 weeks of its start, the bonus will be $ 500. Find the probability of eachbonus.