A supplier of parts to an assembly plant in the household appliance industry is required to make
Question:
(a) The economic batch size and
(b) The total annual inventory cost for the data. It is desired to reduce the batch size from the value determined in part (a) to 200 units, consistent with the daily quantity delivered to the appliance assembly plant.
(c) Determine the changeover time that would allow the economic batch size in stamping to be 200 pieces.
(d) What is the corresponding total annual inventory cost for this batch size, assuming the changeover time in part (c) Can be realized?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Automation Production Systems and Computer Integrated Manufacturing
ISBN: 978-0132393218
3rd edition
Authors: Mikell P.Groover
Question Posted: