An insurance claims work area has five claims waiting for processing as follows. Compute the average flow

Question:

An insurance claims work area has five claims waiting for processing as follows.
An insurance claims work area has five claims waiting for

Compute the average flow time, tardiness, and lateness for the following sequences:
SPT sequence, EDD sequence, and the sequence 2-1-5-3-4. What sequencing rule do you recommend and why?