An operation has a 90% learning curve and the first unit produced took 28 minutes. The labor

Question:

An operation has a 90% learning curve and the first unit produced took 28 minutes. The labor cost is $20 per hour.
(a) How long will the second unit take?
(b) How much should the second unit cost?