Answer the following questions for the network shown below Times
Answer the following questions for the network shown below. Times shown are in days.
a. What is the length of the critical path?
b. What are the earliest start and latest start for E?
c. What is the latest start for B?
d. If all other tasks are completed in their expected durations, would the project length be affected if task B actually takes 5 days instead of the expected 3?
Membership TRY NOW
  • Access to 800,000+ Textbook Solutions
  • Ask any question from 24/7 available
    Tutors
  • Live Video Consultation with Tutors
  • 50,000+ Answers by Tutors
OR
Relevant Tutors available to help