At the start of 2015, Textile Express Company determined its standard labor cost to be 2.25 hours

Question:

At the start of 2015, Textile Express Company determined its standard labor cost to be 2.25 hours per unit at $12.00 per hour. The budget for variable overhead was $9 per unit, and budgeted fixed overhead was $15,000 for the year. Expected annual production was 6,000 units. During 2015, the actual cost of labor was $14.25 per hour. Textile Express produced 4,600 units requiring 11,700 direct labor hours. Actual overhead for the year was $50,000.

Required

Calculate labor rate and efficiency variances and the controllable overhead variance and the overhead volume variance.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: