Baker Construction acts as the general contractor on building projects ranging from $500,000 to $5 million. Each
Question:
Required:
1. Given the preceding information, what is the markup percentage on total direct costs?
2. Suppose Baker is asked to bid on a job with estimated direct costs of $980,000. What is the bid? If the customer complains that the profit seems pretty high, how might Baker counter thataccusation?