Question: Because Landon Corporation see Problem 19 is being pressured to

Because Landon Corporation (see Problem 19) is being pressured to complete the product development project at the earliest possible date, the project leader requested that the possibility of crashing the project be evaluated.
a. Formulate a linear programming model that could be used in making the crashing decisions.
b. What information would have to be provided before the linear programming model could be implemented?