Because of a rapid growth in population, a small town in Pennsylvania is considering several options to

Question:

Because of a rapid growth in population, a small town in Pennsylvania is considering several options to establish a wastewater treatment facility that can handle upto a flow of 2 million gallons per day (MGD). The town has five treatment options available.
• Option 1: No action. This option will lead to continued deterioration of the environment. If growth continues and pollution results, fines imposed (as high as $10,000 per day) would soon exceed construction costs.
• Option 2: Land-treatment facility. This option will provide a system for land treatment of the wastewater to be generated over the next 20 years and will require the utilization of the most land for treatment of the wastewater. In addition to the need to find a suitable site, pumping of the wastewater for a considerable distance out of town will be required. The land cost in the area is $3,000 per acre. The system will use spray irrigation to distribute wastewater over the site. No more than 1 inch of wastewater can be applied in one week per acre.
• Option 3: Activated sludge-treatment facility. This option will provide an activated sludge-treatment facility at a site near the planning area. No pumping will be required, and only seven acres of land will be needed for construction of the plant, at a cost of $7,000 per acre.
• Option 4: Trickling filter-treatment facility. Provide a trickling filter-treatment facility at the same site selected for the activated sludge plant of option 3. The land required will be the same as that for option 3. Both facilities will provide similar levels of treatment but will be using different units.
• Option 5: Lagoon-treatment system. Utilize a three-cell lagoon system for treatment. The lagoon system requires substantially more land than options 3 and 4 require but less than option 2. Due to the larger land requirement, this treatment system will have to be located some distance outside of the planning area and will require pumping of the wastewater to reach the site.
Table ST 16.3 summarizes, respectively, (1) the land cost and land value for each option, (2) the capital expenditures for each option, and (3) the O&M costs associated with each option.
The price of land is assumed to be appreciating at an annual rate of 3%, and the equipment installed will require a replacement cycle of 15 years. Its replacement cost will increase at an annual rate of 5% (over the initial cost), and its salvage value at the end of each replacement cycle will be 50% of the original replacement cost. The structure requires replacement after 40 years and will have a salvage value of 60% of the original cost. The cost of energy and repair will increase at an annual rate of 5% and 2%, respectively. The labor cost will increase at an annual rate of 4%.
With the following sets of assumptions, answer parts (a) and (b).
• Assume an analysis period of 120 years.
• Replacement costs for the equipment, as well as for the pumping facilities, will increase at an annual rate of 5%. Salvage Value
Salvage value is the estimated book value of an asset after depreciation is complete, based on what a company expects to receive in exchange for the asset at the end of its useful life. As such, an asset’s estimated salvage value is an important...