Calculate the fully loaded cost of labor for a project team member using the following data: Hourly

Question:

Calculate the fully loaded cost of labor for a project team member using the following data:
Hourly rate ………………………..$35/hr.
Hours needed…………………….150
Overhead rate …………………….55%