Chris Millikan Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the

Question:

Chris Millikan Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.

Setup cost = $30

Annual holding

Cost = $120 per subassembly

Daily production = 20 subassemblies

Annual usage = 2,500 (50 weeks x 5 days each

X daily usage of 10 subassemblies)

Lead time = 16 days,

Safety stock = 4 days’ production of subassemblies.