Classy Attire the designer and maker of elaborate prom dresses. The president of Classy wants to switch to an activity-based approach in the upcoming year to assign prices to the gowns. Production line setups are a major activity at Classy. Next year Classy expects to perform 1,500 setups at a total cost of $93,000. Classy plans to produce 310 dresses of the A128 design, which will require three setups.

Required
How much setup cost will be allocated to each dress of the A128 design that is produced?



$1.99