Compute the activity cost rates for materials handling, assembly, and design based on these data: Materials Cloth..........$26,000

Question:

Compute the activity cost rates for materials handling, assembly, and design based on these data:

Materials

Cloth..........$26,000

Fasteners........4,000

Purchased parts.....40,000

Materials Handling

Labor.......... 8,000

Equipment depreciation... 5,000

Electrical power...... 2,000

Maintenance...... 6,000

Assembly

Machine operators...... 5,000

Design

Labor ......... 5,000

Electrical power......1,000

Overhead........8,000

Output totaled 40,000 units. Each unit requires three machine hours of effort. Materials handling Costs are allocated to the products based on direct materials cost. Design costs are allocated based on units produced. Assembly costs are allocated based on 500 machine operator hours.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Principles of Accounting

ISBN: 978-1439037744

11th Edition

Authors: Needles, Powers, crosson

Question Posted: