Computing materials, labor, and manufacturing overhead cost variances Frank Trawick was a new cost accountant at Skoney

Question:

Computing materials, labor, and manufacturing overhead cost variances Frank Trawick was a new cost accountant at Skoney Plastics Corporation. He was assigned to analyze the following data that his predecessor left him.


10,000 units 2 lbs. @ $1.50 per pound 0.5 hours @ $10.00 per hour Planned volume for year (static budget) Standard direc


Required
a. Prepare a materials variance information table showing the standard price, the actual price, the standard quantity, and the actual quantity.
b. Calculate the materials price and usage variances and indicate whether they are favorable (F) or unfavorable (U).
c. Prepare a labor variance information table showing the standard price, the actual price, the standard hours, and the actual hours.
d. Calculate the labor price and usage variances and indicate whether they are favorable (F) or unfavorable (U).
e. Calculate the predetermined overhead rate, assuming that Skoney Plastics uses the number of units as the allocation base.
f. Calculate the fixed manufacturing overhead cost spending variance and indicate whether it is favorable (F) or unfavorable (U).
g. Calculate the fixed manufacturing overhead cost volume variance and indicate whether it is favorable (F) or unfavorable (U).