Consider the following software development plan. a. The client has asked for an estimated completion date. What

Question:

Consider the following software development plan.


a. The client has asked for an estimated completion date. What would you tell her?
b. The client would like to have the completed software in 37 weeks. What is the likelihood that the critical path will be completed in that time frame?
c. The client has just asked if it would be possible to have the completed software in 36 weeks. What is the likelihood the project will be completed in that time frame?
d. The client wants to know if it would be possible to complete the project in 33 weeks. What is the probability of meeting the client’s demand?
e. You are concerned about the accuracy of your calculations because the paths are not independent. What is the likelihood that all of the coding activities will be completed on time?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managing Operations Across the Supply Chain

ISBN: 978-0078024030

2nd edition

Authors: Morgan Swink, Steven Melnyk, Bixby Cooper, Janet Hartley

Question Posted: