Question: Consider the Western Hills Shopping Center Project summarized by Figure

Consider the Western Hills Shopping Center Project summarized by Figure 13.6 and Table 13.2. Suppose the project has been underway for seven weeks. Activities A and E have been completed. Activity F has commenced but has three weeks remaining. Activities C and D have not started yet. Activity B has one week remaining (it was not started until week 2). Update the activity schedule for the project. In particular, how has the slack for each activity changed?