Question

Craig, Inc., has provided the following information for one of its products for each hour of
production:
Actual velocity: 100 units (per hour)
Move time: 20 minutes
Inspection time: 18 minutes
Rework time: 12 minutes
Required:
1. Calculate MCE. Comment on its significance.
2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times.
3. What if waste is reduced by 40 percent? What is the new MCE? New cycle time?


$1.99
Sales0
Views100
Comments0
  • CreatedSeptember 01, 2015
  • Files Included
Post your question
5000