Question

Data pertaining to job cost sheets for Dieker Company are given in BE20-3 and BE20-4. Prepare the job cost sheets for each of the three jobs.
In BE20-4, Factory labor data for Dieker Company is given in. During January, time tickets show that the factory labor of $6,000 was used as follows: Job 1 $2,200, Job 2 $1,600, Job 3 $1,400 and general factory use $800.
In BE20-3, In January, Dieker Company requisitions raw materials for production as follows: Job 1 $900, Job 2 $1,200, Job 3 $700 and general factory use $600. Prepare a summary journal entry to record raw materials used.