Draw a project network from the following information. Activities B and H can be shortened to a

Question:

Draw a project network from the following information.


Draw a project network from the following information.  .:.

Activities B and H can be shortened to a minimum of 2 weeks. Which activity would you shorten to reduce the project duration by 2 weeks?Why?