Find (a) The AOA network and the critical path. (b) All event slacks. (c) Critical path to
Question:
(a) The AOA network and the critical path.
(b) All event slacks.
(c) Critical path to event D.
(d) Critical path probability of completion in 14 days.
(e) The effect if CD slips to 6 days; to 7 days; to 8days.
Transcribed Image Text:
b-9763868017 m-6433205414 a-3103202411 EDEFE
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 50% (16 reviews)
a The critical path is AC CB BE EF b The only event with slack is D at 3 days c If D were t...View the full answer
Answered By
Talha Talib
I am a member of IEEE society. As i am a student of electrical engineering badge 17 but beside of this i am also a tutor in unique academy. I teach calculus, communication skills, mechanics and economics. I am also a home tutor. My student Muhammad Salman Alvi is a brilliant A-level student and he performs very well in academics when i start to teach him. His weak point was mathematics but now he is performing well in mathematics. I am a scholarship holder in Fsc as i scored 1017 marks in metric out of 1100. Later on i got scholarship in Punjab Group of Colleges. I got 2nd position in robotics competition in 2018 as my project home automation select for the exhibition in Expocentre.
4.60+
23+ Reviews
62+ Question Solved
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Question Posted:
Students also viewed these Management Leadership questions
-
Find a, b, c and d if (a) (b) (c) (d) a b b-c 3 1 2 2
-
If the probability that an event E occurs is 3 7, what are the odds that (a) E will occur? (b) E will not occur?
-
C and D are equal partners in the CD partnership. C starts the year with an adjusted basis of $300 in his partnership interest while D starts the year with an adjusted basis of $600. The partnership...
-
Use the Ratio Test to determine the values of x 0 for which each series converges. 00 X' k=0
-
Seneca Co. began year 2016 with 6,500 units of product in its January 1 inventory costing $35 each. It made successive purchases of its product in year 2016 as follows. The company uses a periodic...
-
A woman travels to work by bicycle 70% of the time and by scooter 30% of the time. If she uses her bicycle she is late 3% of the time but if she uses her scooter she is late only 2% of the time. a....
-
The basic purpose of a heat engine is to convert (a) Mechanical energy into thermal energy (b) Thermal energy into electrical energy (c) Thermal energy into mechanical energy (d) None of these.
-
Selected accounts of Sandin Company are shown here. InstructionsAfter analyzing the accounts, journalize (a) The July transactions and (b) The adjusting entries that were made on July31. Supplies...
-
A large hospital required nurses to work 80 hours over two-week (14 day) pay periods. In addition, nurses were also considered to be "on-call" for an additional 20 hours during the pay period. While...
-
Sunnyside Solar Consultants provided $180,000 of consulting services to Delton Developments on April 14, 2020, on account. Required Journalize Sunnyside?s April 14 transaction including applicable...
-
Given the estimated activity times below and the network in Problem 8 above, what is the critical path probability that the project will be completed within: (a) 21 days? (b) 22 days? (c) 25days?...
-
a. Draw the AOA diagram. b. Find the critical path. c. Find the completion time. Activity TE AB .....1 AC .....2 AD .....3 DC .....4 CB .....3 DE .....8 CF .....2 BF .....4 IJ .......2 CE .....6 EF...
-
A survey done for the Bermuda tourist industry reported that the average cruise ship visitor to Bermuda spends $185 for souvenirs, etc. (source: BermudaSun.org). Assume the distribution of visitor...
-
The carrying value of the Annuities Payable account of a college a. should be adjusted to reflect changes in actuarial assumptions such as life expectancies or yield estimates. b. should be adjusted...
-
Why is it important to understand the complexities in lines of communication?
-
Do you believe that individuals such as the defendant's spouse, priest, doctor, or lawyer should or should not be compelled to testify against the defendant? What are the arguments in favor of...
-
How can a run chart be used within a project environment?
-
Why is the definition of quality critical to the success and acceptance of a project?
-
The financial year of Liz King ended on 31 December 2011. From the following information, ascertain the amounts to be included in the statement of comprehensive income for the year ended 31 December...
-
Determine the values of the given trigonometric functions directly on a calculator. The angles are approximate. tan 0.8035
-
An insurance company in Asia reported profit of $100 million for the financial year through the news-dissemination system of the stock exchange. Its stock price increased several times, as the...
-
Explain how useful each of the following can be during the estimating of project costs: a. Contingency planning and estimating b. Using historical databases c. Usefulness of computer estimating d....
-
On June 12, 2002, Delta Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, and the remaining $17,000 was profit. The...
-
Acme Corporation has received a contractual order to build a new tooling machine for Alpha Corporation. The project started several months ago. Table 1514 is the Monthly Cost Summary for June, 2002....
-
Find the instantaneous rate of change of the function f(t)=3+5t when t=-3.
-
Pretend you need to conduct a title search. You have the information needed from your online search, but you need to go to the clerk's office to finish your search. What information/records will/can...
-
Watch the Tedx Talk (Melvin Russell: I love being a police officer, but we need reform) by Lt. Colonel Melvin Russel from the Baltimore Police. In his talk, he discusses how law enforcement is in...
Study smarter with the SolutionInn App