Five years ago, the City of Paranoya spent $30,000 to purchase a computerized radar system called W.A.S.T.E.

Question:

Five years ago, the City of Paranoya spent $30,000 to purchase a computerized radar system called W.A.S.T.E. (Watching Aliens Sent To Earth). Recently, a sales rep from W.A.S.T.E. Radar Company told the city manager about a new and improved radar system that can be purchased for $50,000. The rep also told the manager that the company would give the city $10,000 in trade on the old system. The new system will last 10 years. The old system will also last that long but only if a $4,000 upgrade is done in 5 years. The manager assembled the following information to use in the decision regarding which system is more desirable:


Old System New System Cost of radar system $30,000 $50,000 Current salvage value $10,000 $5,000 Salvage value in 10 year


Required:
What is the City of Paranoya's net present value for the decision described above? Use the total costapproach.

Net Present Value
What is NPV? The net present value is an important tool for capital budgeting decision to assess that an investment in a project is worthwhile or not? The net present value of a project is calculated before taking up the investment decision at...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost Management Accounting and Control

ISBN: 978-0324559675

6th Edition

Authors: Don R. Hansen, Maryanne M. Mowen, Liming Guan

Question Posted: