Question

For the Solved Problem above, assume that the most likely times (m) are the normal activity times and the optimistic times (a) are the activity crash times. Further assume that the activities have the following normal and crash costs:

Activity Costs (Normal Cost, Crash Cost)
1......... ($100, 400)
2.......... ($250, 400)
3.......... ($400, 800)
4.......... ($200, 400)
5. .......... ($150, 300)
6. .......... ($100, 100)
7.......... ($300, 500)

Crash the network the maximum amount possible and indicate the total crash cost.



$1.99
Sales0
Views139
Comments0
  • CreatedApril 10, 2014
  • Files Included
Post your question
5000