Given the following information on job times and due dates, determine the optimal processing sequence using (1)

Question:

Given the following information on job times and due dates, determine the optimal processing sequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each method, find the average job flow time and the average job tardiness. Jobs are listed in order ofarrival.