Given the following project (all times are in days): (a) Draw the network and find the critical

Question:

Given the following project (all times are in days):


Given the following project (all times are in days):


(a) Draw the network and find the critical path, time, and cost for an all-normal level of project activity.
(b) Calculate the crash cost-per-day (all activities may be partially crashed).
(c) Find the optimal way of getting an 18-day delivery time. What is the project cost?
(d) Find the optimal way of getting a 16-day delivery time. What is the project cost?
(e) Calculate the shortest delivery time for the project.
What is thecost?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Managerial Approach

ISBN: 978-0470226216

7th Edition

Authors: Jack R. Meredith, Samuel J. Mantel,

Question Posted: