Given the network below, compute the early, late, and slack time for each activity. Clearly identify the

Question:

Given the network below, compute the early, late, and slack time for each activity. Clearly identify the critical path.

Lag 1 Build Install Cabinets Cabinets A Lag 5 Design B Tear Down 3 Install Appliances Inspect Lag 2 2 Lag 5 Order Legend