Question: Goldman Inc manufactures lead crystal glasses The standard direct labor

Goldman, Inc. manufactures lead crystal glasses. The standard direct labor time is 0.5 hours per glass, at a cost of $17 per hour. The actual results for one month’s production of 6,900 glasses were 0.2 hours per glass, at a cost of $11 per hour. Calculate the direct labor cost variance and the direct labor efficiency variance.