Question

Hiawatha Hydrant Company manufactures fire hydrants in Oswego, New York. The following information pertains to operations during May.
Processing time (average per batch)...................... 4.25 hours
Inspection time (average per batch)....................... .25 hour
Waiting time (average per batch)........................... .25 hour
Move time (average per batch)............................... .25 hour
Units per batch........................................................ 20 units

Required:
Compute the following operational measures:
(1) Manufacturing cycle efficiency;
(2) Manufacturing cycle time;
(3) Velocity.



$1.99
Sales4
Views487
Comments0
  • CreatedApril 22, 2014
  • Files Included
Post your question
5000