Hoschild Bicycle Company manufactures bicycles. The following data for September of the current year are available: Quantity

Question:

Hoschild Bicycle Company manufactures bicycles. The following data for September of the current year are available:

Quantity of direct labor used ........ 850 hrs.

Actual rate for direct labor ......... $ 15.60 per hr.

Bicycles completed in September ...... 400

Standard direct labor per bicycle ....... 2 hrs.

Standard rate for direct labor ....... $ 16.00 per hr.

a. Determine the direct labor rate and time variances.

b. How much direct labor should be debited to Work in Process?


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Financial and Managerial Accounting

ISBN: 978-1285078571

12th edition

Authors: Carl S. Warren, James M. Reeve, Jonathan Duchac

Question Posted: