If the TOL file cabinet has a gross materials requirements plan as shown below, no inventory, and

Question:

If the TOL file cabinet has a gross materials requirements plan as shown below, no inventory, and 2 weeks of lead time is required for assembly, what are the order release dates and lot size when lot sizing is determined using PPB (part period balancing)? Use a holding cost of $2.00 and a setup cost of $20,000, and no initial inventory.
If the TOL file cabinet has a gross materials requirements
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: