In 2010 Dreyer Corporation began construction work under a three year
In 2010, Dreyer Corporation began construction work under a three-year contract. The contract price is $800,000. Dreyer uses the percentage-of-completion method. The financial statement presentations relating to this contract on December 31, 2010 follow:


Required
1. How much cash did Dreyer collect during 2010?
2. What was the initial estimated total income before tax on thiscontract?