In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in year 2015. During March 2015, Shire began and completed Job No. 13-56.
1. What is the predetermined overhead rate for 2015?
2. Use the information on the following job cost sheet to determine the total cost of the job.