Question: In Pargo Company s flexible budget graph the fixed cost line

In Pargo Company’s flexible budget graph, the fixed cost line and the total budgeted cost line intersect the vertical axis at $90,000. The total budgeted cost line is $350,000 at an activity level of 50,000 direct labor hours. Compute total budgeted costs at 65,000 direct labor hours.