In September 2009, a 3.45 megawatt cooling, heating, and power (CHP) system was placed in into operation
Question:
• Installed cost: $2.5 million
• Annual energy cost savings: $786,000
• Annual O&M costs: $233,000
• Project service life: 15 years
• Salvage value: $200,000
At an interest rate of 8%, what is the net savings per dollar invested?
Salvage Value
Salvage value is the estimated book value of an asset after depreciation is complete, based on what a company expects to receive in exchange for the asset at the end of its useful life. As such, an asset’s estimated salvage value is an important...