In the transfer line of Problems 16.20 and 16.22, suppose it is more technically feasible to locate
Question:
(a) The maximum possible line efficiency and production rate that would result from installing the storage buffer, and
(b) The line efficiency and production rate for a storage buffer with a capacity of 20 parts.
Assume that downtime (Td = 6.0 min) is a constant.