Jamie is planning a trip overseas. A variety of activities must be completed before her departure. The

Question:

Jamie is planning a trip overseas. A variety of activities must be completed before her departure. The following table describes the relationships between these activities.
Activity Immediate Predecessors
A -
B A
C A
D B, C
E B, C
F D, E
G F
Jamie was able to estimate the activity times as shown in the table below.
Activity Time (Days)
A 4
B 4
C 5
D 3
E 3
F 2
G 1
Using the above information to answer the following questions
1) Using this data above, draw a network for this project.
2) Calculate the earliest and latest start and finish times for each activity.
3) Calculate the slack for each activity.
4) Determine the length of the project and the critical path.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Decision Modeling With Spreadsheets

ISBN: 9780136115830

3rd Edition

Authors: Nagraj Balakrishnan, Barry Render, Jr. Ralph M. Stair

Question Posted: