Jerris Jackets produces an item that gives rise to the following activities: Activity Hours Processing (two departments)
Question:
Activity Hours
Processing (two departments) ....... 45.0
Inspecting ................. 3.0
Rework ..................... 7.5
Moving (three moves) .......... 12.0
Waiting (for the second process) ...... 36.0
Storage (before delivery to the customer) ... 46.5
Required
A. Calculate the manufacturing cycle time for the item.
B. Calculate the manufacturing cycle efficiency for the item.