Job 19AB required $10,000 for direct materials, $4,000 for direct labor, 300 direct labor hours, 150 machine hours, three setups, and five design changes. The cost pools and overhead rates for each pool follow:
Cost Pool Overhead Rate
Direct labor support $10/direct labor hour
Machining support $15/machine hour
Machine setups $350/setup
Design changes $700/design change
Determine the cost of Job 19AB.