LaCrosse, Inc., sales manager Josh Brown has been receiving calls from customers complaining about the length of
Question:
_________________________________________Days required
Process customer order........................................................0.2
Wait for direct materials to arrive........................................3.0
Fabrication of parts..............................................................3.0
Move order to assembly department....................................0.6
Wait for machine time..........................................................6.0
Assembly of parts.................................................................4.0
Move order to finishing department.....................................0.5
Wait for machine time..........................................................3.0
Finishing of units..................................................................5.0
Move to packing department................................................0.5
Packing.................................................................................1.5
Move to shipping department...............................................0.2
Load delivery truck..............................................................0.5
Drive to customer.................................................................1.0
Unload delivery truck...........................................................0.5
Return to plant......................................................................1.0
(a) Calculate the delivery cycle time for DanGold's order.
(b) Calculate the manufacturing cycle time for DanGold's order.
(c) Calculate the value-added time for DanGold's order.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer: