Material requirements are to be planned for component C2 given the master schedule for P1 and P2,

Question:

Material requirements are to be planned for component C2 given the master schedule for P1 and P2, and the product structures in. Assembly lead time for products and subassemblies (P and S levels) is 1 week, manufacturing lead times for components (C level) is 2 weeks, and ordering lead time for raw materials (M level) is 3 weeks. Determine the time phased requirements for M2, C2, and S1. Assume there are no common use items other than those specified by the product structures for P1 and P2, and that all on-hand inventories and scheduled receipts are zero. Use a format similar to Figure 25.7. Ignore demand beyond period 10.