Sid Davidson was able to determine the activity times for the leadership training program. He would like

Question:

Sid Davidson was able to determine the activity times for the leadership training program. He would like to determine the total project completion time and the critical path. The activity times appear in the following table:
ACTIVITY TIME (DAYS)
A ............ 2
B ............ 5
C ............ 1
D ............ 10
E ............ 3
F ............ 6
G ............ 8
35

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis for Management

ISBN: 978-0132149112

11th Edition

Authors: Barry render, Ralph m. stair, Michael e. Hanna

Question Posted: