Nick, the owner of a steel company currently has five jobs to be scheduled, shown in the

Question:

Nick, the owner of a steel company currently has five jobs to be scheduled, shown in the order in which they arrived. Show your supporting calculations in detail.


Nick, the owner of a steel company currently has five


a. Which dispatching rule has the best score for flow time?
b. Which dispatching rule has the best score for work-in-process (jobs in the system)?
c. Which dispatching rule has the best score for lateness?
d. What dispatching rule would you select? Support your decision.
e. Complete the followingtable.