North Manchester Foundry produced 55,000 tons of steel in March at a cost of 1,150,000. In April,

Question:

North Manchester Foundry produced 55,000 tons of steel in March at a cost of £1,150,000. In April, the foundry produced 35,000 tons at a cost of £950,000. Using only these two data points, determine the cost function for North Manchester.